In August 2007 Iran and the International Atomic Energy Agency (IAEA) agreed to a work plan (INFCIRC/711) for resolving all outstanding questions concerning Iran’s past nuclear activities. We illustrated in a past Proliferation Analysis entitled "Iran's Plan for Nuclear Compliance" that the timeline proposed by the Iran-IAEA deal would allow Iran about eight months of continued centrifuge installation and operations, but that it failed to appropriately address certain issues, in particular the 1987 uranium metal document received from Pakistan. We did not include any dates for resolution of Iran's "alleged studies"—the Green Salt Project, high explosive testing, and the design of a missile re-entry vehicle—because Iran categorically rejected considering them.
The February IAEA safeguards report on Iran (GOV/2008/4) indicates that the answers provided by Iran on all but two issues are "consistent" or "not inconsistent" with its information and on schedule (if not earlier) with the agreed-upon work plan. However, the final outstanding issues are those most closely associated with weaponization. An illustration of Iran’s progress shows that questions regarding its alleged weaponization studies and uranium metal will likely remain contested issues into April 2008 and beyond. (See below for a side-by-side comparison of INFCIRC/711 and GOV/2008/4.)
Comparing Iran’s Nuclear Compliance: INFCIRC/711 and GOV/2008/4
How close is Iran in complying with the Iran-IAEA work plan?
|
IAEA PROVIDES QUESTIONS |
MEETING IN IRAN TO DISCUSS |
CLOSURE |
|||
INFCIRC/711//GOV/2008/4 |
INFCIRC/711 |
GOV/2008/4 |
INFCIRC/711 |
GOV/2008/4 |
||
Plutonium |
July 23 |
July |
July |
August 20 |
August 20 |
|
P1/P2 |
August 31 |
September |
September 24 |
November |
November |
|
HEU Contamination |
September 15 |
2 weeks after P1/P2 closure (mid-November) |
December 10-12 |
January |
January 8 |
|
Uranium Metal |
INFCIRC/711: Iran agrees to facilitate comparison of sections of uranium metal document after which IAEA will close issue. |
|||||
Po-210 |
September 15 after all other questions closed. |
2 weeks after HEU Contamination/ |
January |
March* |
February 22 |
|
Ghachine Mine |
September 15 |
2 weeks after Po-210 closure (February 22) |
January |
April* |
February 22 |
|
Alleged Studies |
INFCIRC/711: Iran finds allegations as “baseless” and “political motivated” but will review IAEA-provided documents. |
*These dates were Carnegie estimates for possible issue closure, based on the text of INFCIRC/711. The IAEA indicated in GOV/2008/4 that it no longer considered the Po-210 and Ghachine mine issues to be outstanding.
Click here to download the PDF version of the above table.